How to Set Up and Use Budgets in Raken

In this article, learn how to set up project budgets in Raken, track hours and quantities against them, and see progress through Efficiency, % Completed, and Projected Hours.

Budgets let you set planned hour and quantity targets for each cost code on a project, then track how actual field entries compare to those targets in real time. Once a budget is in place, Raken automatically calculates Efficiency, % Completed, and Projected Hours as your team logs time, materials, and quantities against that cost code.


Quick Answer

To set up a budget in Raken:

  1. Log into the Raken web app and open a Project.

  2. Click Settings, then Production, then Budgets.

  3. Click + Add budget, select a cost code, and enter budgeted hours and/or budgeted quantity.

  4. Click Save. The budget is active immediately.

Budgets and Production Tracking require the Performance Plan.


How to Add a Budget

Step 1: Set Up Cost Codes First

Budgets are built on top of cost codes, so cost codes must exist before you can budget against them. See How to Set Up Cost Codes in Raken if you haven't set these up yet.

Step 2: Navigate to Project Budgets

Open the Raken web app and navigate to the project you want to budget. Click Settings at the bottom left, then Production, then Budgets.

Step 3: Add a Budget Manually

Click + Add budget. Select the cost code you want to budget, then enter the budgeted hours and/or budgeted quantity for that code. Click Save.

Step 4: Repeat for Each Cost Code

Add a budget entry for every cost code you want to track progress against on this project. Cost codes without a budget entry can still be used for time and material logging, they just won't show budget-based calculations like % Completed.


How to Import Budgets in Bulk

From the Budgets screen, click Upload budgets to download the CSV template. Fill in your budgeted hours and/or quantities for each cost code, then upload the completed file. This is the faster option for projects with a large number of cost codes to budget at once.


How Budget Progress Is Calculated and Displayed

Once a budget is set up, Raken calculates three figures automatically as time cards and material entries are logged against that cost code:

  • Efficiency — how actual hours or quantity compare to what was budgeted.

  • % Completed — how far along the cost code is relative to its budgeted target.

  • Projected Hours — an estimate of total hours needed to finish, based on progress so far.

These figures appear in Production Insights and on the Production section of the daily report PDF.

For the Production section to appear on the daily report PDF at all, three things must be logged against the same cost code: a budget, a time card, and a material entry. Missing any one of the three keeps the section off the PDF.

Note: % Completed caps at 100% in reports, even if actual hours or quantity logged exceed the original budgeted amount. If a cost code is running over, that will still be visible by comparing the Actual and Budgeted columns directly, just not as a percentage above 100%.


Who Can Set Up and Edit Budgets

Budget setup is controlled by a dedicated permission, separate from general project settings access. Any user whose role has the "Can create/edit/delete budgets" permission enabled can add, edit, and delete budgets. An Account Administrator can enable this permission for a role under Company > Roles & Permissions.


Troubleshooting & FAQ

I set up a budget, but I don't see % Completed or Efficiency anywhere. Why?

These figures only calculate once there's actual field activity to compare against the budget. Confirm a time card and a material entry have both been logged against the same cost code as the budget.

Are budgets set at the company level or the project level?

Project level. Each project has its own independent set of budgets, even if the underlying cost codes are shared company-wide. Setting a budget on one project does not affect any other project.

Can I set a dollar-amount budget instead of hours or quantity?

No. Budgets in Raken are tracked by hours and/or quantity per cost code, there is currently no dollar-amount budget field.

Can I create or update budgets through the Public API?

Not currently. The Public API supports listing existing budgets for a project, but does not support creating or updating them. Budgets need to be added manually or via the CSV bulk upload inside the Raken web app.

A new cost code I just added isn't showing up as an option to budget against.

Confirm the cost code is enabled on this specific project first. Cost codes added at the company level only apply automatically to new projects, existing projects need the code enabled individually under Settings > Production > Cost codes. See How to Set Up Cost Codes in Raken.


Technical Specifications

  • Compatibility: Web app (setup); web and mobile app for viewing progress (iOS 15+, Android 10+)

  • Offline Capability: No — budget setup requires an active connection

  • Plan Required: Performance Plan

  • Role Required: Any role with the "Can create/edit/delete budgets" permission enabled


Considerations

  • Budgets and Production Tracking require the Performance Plan.

  • Budgets are set at the project level, not the company level. Each project has its own set of budgets.

  • Cost codes must exist, and be enabled on the project, before they can be budgeted against.

  • Budgets track hours and/or quantity only, there is no dollar-amount budget field.

  • % Completed caps at 100% even when actual hours or quantity exceed budget.

  • Budgets can be listed via the Public API, but not created or updated through it.

  • For the Production section to appear on the daily report PDF, a budget, a time card, and a material entry must all be logged against the same cost code.