In this article, learn how to generate and export the RFI report in Raken to track question status, response counts, and overdue items across a project.

The RFI report gives you a complete, exportable log of every Request for Information on a project — where each one stands, how long it's been open, and who's responsible for the next response.


Quick Answer

To run the RFI report:

  1. Log into the Raken web app. Click Projects and open your project.

  2. Click the Reports button in the top right corner and select RFI.

  3. Select your Project, enter the recipient email in Send to, and click Send.

The RFI report requires the Performance Plan. It's send-once only — there's no Scheduled tab for recurring delivery.


RFI Report

The RFI report exports a PDF log of all requests for information on a selected project. It includes each RFI's number, title, assignees, due date, response count, and status — along with a summary showing total closed, total open, and total overdue RFIs.

How to Run

  1. Click Reports and select RFI.

  2. Select your Project from the dropdown.

  3. Enter the recipient email address in Send to.

  4. Click Send.

The modal goes straight to this form — there are no "Run once" or "Scheduled" tabs the way some other reports have.

Format: PDF

Delivery: Email — you will receive a message from Raken with a download link to the PDF file.


Troubleshooting & FAQ

The RFI report shows no RFIs — why?

The RFI report reflects RFIs that have been created on the selected project. If no RFIs have been logged, the report PDF will show empty columns and zero totals.

Can the RFI report be scheduled to run automatically?

No. The RFI report is send-once only — there's no Scheduled tab in the report modal. It must be run manually each time you need it.

Can I run the RFI report across multiple projects at once?

No — the RFI report is project-specific. Select a single project when running it. To review RFIs across your whole company, use Company > RFIs for a master list instead.


Technical Specifications

  • Compatibility: Web app only

  • Offline Capability: No — requires an active connection

  • Delivery method: Email (from no-reply@rakenapp.com), send-once only, no scheduled delivery

  • File format: PDF

  • Plan Required: Performance Plan

  • Role Required: Account Administrator or Project Administrator


Considerations

  • The RFI report requires the Performance Plan.

  • RFI reports are project-specific — select a single project when running the report.

  • There's no Scheduled tab for this report — it's send-once only, confirmed via screenshot Sept 10, 2026.

  • For a cross-project view of all RFIs, use Company > RFIs instead of this report.


More Questions?

Feel free to email us or call us at +1 866-438-0646. We're always glad to answer your questions!

Did this answer your question?