Manually exporting data from CMiC and re-entering it in Raken is time-consuming and error-prone. The Raken + CMiC Enterprise integration eliminates that work — automatically keeping your Employees, Projects, Cost Codes, and Classifications in sync, and making payroll exports a single click. The V2 release adds Daily Journal Sync and Project Partners sync for clients who need deeper project management data connectivity.
How the Integration Works
Once integrated, Raken and CMiC sync every 30 minutes to keep your data accurate and current. Your resource lists stay up to date in both systems without manual maintenance.
When it's time to process payroll, you can push Time Cards from Raken back to CMiC with the click of a button.
The integration maps the following data between systems:
CMiC → Raken: Employees, Projects, Cost Codes, Unions and Trades (Classifications), Project Partners (Contact Companies — opt-in)
Raken → CMiC: Time Cards (on-demand export), Daily Reports/Notes/Work Logs/Attachments/Weather as Daily Journals (opt-in)
Integration Setup Process
A Raken Customer Success Manager who specializes in integrations will guide your team through the entire process. Setup is handled collaboratively with a Raken integration specialist — there is no self-serve configuration.
Phase 1: Preparation
A Raken integration specialist will assist your organization in preparing both your CMiC and Raken accounts for the integration and gathering all the information needed for a successful setup.
Phase 2: Onboarding
Your Raken specialist will guide your team through the configuration steps that allow data from CMiC to sync directly with Raken.
Phase 3: Implementation
Your Raken specialist will confirm that all desired data is in Raken and that relevant team members are trained on how to operate Raken using the integration long-term.
Ready to get started? Request integration access here.
Requirements
CMiC (core integration): An active subscription to CMiC Enterprise or CMiC Cloud, plus API access for the HCM, JC, and Payroll modules.
CMiC (V2 opt-in features): The Project Management (PM) or PM Construct module is required in addition to the core modules above to use Daily Journal Sync and Project Partners sync.
Raken: An active Raken Performance Plan account. Daily Journal Sync and Project Partners require a Performance Annual or Enterprise plan. Contact your Customer Success Manager to confirm eligibility.
Technical Specifications
Compatibility: Raken web app + CMiC Enterprise or CMiC Cloud
Sync Frequency: Every 30 minutes (inbound); on-demand (time card outbound)
Data Synced In (CMiC → Raken): Employees, Projects, Cost Codes, Unions/Trades (Classifications), Project Partners (opt-in)
Data Synced Out (Raken → CMiC): Time Cards (on-demand); Daily Journals — Reports, Notes, Work Logs, Attachments, Weather (opt-in)
Plan Required: Performance Plan (Daily Journal Sync and Project Partners require Performance Annual or Enterprise)
Role Required: Account Administrator; CSM-guided setup required
Considerations
Setup is guided by a Raken Customer Success Manager — this is not a self-serve integration.
API access must be confirmed and enabled on the CMiC side before integration can begin.
Daily Journal Sync and Project Partners are opt-in and require the CMiC PM or PM Construct module. Contact your CS Manager to enable.
Daily Journal Sync requires the default CMiC Job-Project data structure — Jobs-only setups are not supported.